Expansion of Hong Kong
International Airport into a
Three-Runway System
Construction Phase Quarterly EM&A Report
No.24 (1 October to 31 December 2021)
March 2022
|
|
Contents
1.4 Contact information for the Project
1.5 Summary of Construction Works
1.6 Summary of EM&A Programme Requirements
2 Environmental Monitoring and Auditing
2.1.2 Summary of Monitoring Results
2.2.2 Summary of Monitoring Results
2.3.2 Summary of Monitoring Results
2.4.2 Summary of Monitoring Results
2.4.3 Marine Sediment Management
2.5 Chinese White Dolphin Monitoring
2.5.2 Summary of Monitoring Results
2.6.1 Brief Summary of the Agreed Method
2.6.2 Desk-Based Monitoring Result
2.7 Environmental Site Inspection
2.7.1 Landscape and Visual Mitigation Measures
2.7.2 Land Contamination Assessment
2.8 Audit of SkyPier High Speed Ferries
2.9 Audit of Construction and Associated Vessels
2.10 Review of the Key Assumptions Adopted in the EIA Report
3 Report on Non-compliance, Complaints, Notifications of Summons and Prosecutions
3.1 Compliance with Other Statutory Environmental Requirements
3.2 Analysis and Interpretation of Complaints, Notification of Summons and Status of Prosecutions
3.2.2 Notifications of Summons or Status of Prosecution
4 Conclusion and Recommendation
Tables
Table 1.1: Contact Information of Key Personnel
Table 1.2: Contact Information of the Project
Table 1.3: Summary of Status for All Environmental Aspects under the Updated EM&A Manual
Table 2.1: Impact Air Quality Monitoring Stations
Table 2.2: Percentage of Air Quality Monitoring Results within Action and Limit Levels
Table 2.3: General Meteorological Condition during Impact Air Quality Monitoring
Table 2.4: Impact Noise Monitoring Stations
Table 2.5: Percentage of Noise Monitoring Results within Action and Limit Levels
Table 2.6: General Meteorological Condition during Impact Noise Monitoring
Table 2.7: Monitoring Locations and Parameters for Impact Water Quality Monitoring
Table 2.8: Action and Limit Levels for General Water Quality Monitoring
Table 2.10: Percentage of Water Quality Monitoring Results within Action and Limit Levels
Table 2.11: General Weather Condition and Sea Condition during Impact Water Quality Monitoring
Table 2.12: Summary of SS Compliance Status (Mid-Ebb Tide)
Table 2.13: Summary of SS Compliance Status (Mid-Flood Tide)
Table 2.14: Action and Limit Levels for Construction Waste
Table 2.15: Construction Waste Statistics
Table 2.16: Land-based Theodolite Tracking Survey Station Details
Table 2.17: Derived Values of Action Level and Limit Level for Chinese White Dolphin Monitoring
Table 2.20: Summary of Photo Identification
Table 2.21: Summary of Survey Effort and CWD Group of Land-based Theodolite Tracking Survey
Table 2.22: Landscape and Visual – Construction Phase Audit Summary
Table 2.24: Summary of the Tree Status Updated in the Reporting Period
Table 2.25: Summary of the Transplanted Trees Updated in the Reporting Period 38
Table 2.26: Photos of the Existing Transplanted Trees in the Reporting Period
Table 3.1: Summary of Environmental Complaints
Table 3.2: Statistics for Valid Exceedances for the Environmental Monitoring
Table 3.3: Statistics for Non-compliance, Complaints, Notifications of Summons and Prosecution
Figures
Appendices
Environmental Mitigation Implementation Schedule (EMIS) for Construction Phase |
|
|
3RS |
Three-Runway System |
AAHK |
Airport Authority Hong Kong |
AECOM |
AECOM Asia Company Limited |
AFCD |
Agriculture, Fisheries and Conservation Department |
AIS |
Automatic Information System |
ANI |
Encounter Rate of Number of Dolphins |
APM |
Automated People Mover |
AW |
Airport West |
BHS |
Baggage Handling System |
C&D |
Construction and Demolition |
CAP |
Contamination Assessment Plan |
CAR |
Contamination Assessment Report |
CTCC |
Construction Traffic Control Centre |
CWD |
Chinese White Dolphin |
DCM |
Deep Cement Mixing |
DEZ |
Dolphin Exclusion Zone |
DO |
Dissolved Oxygen |
EIA |
Environmental Impact Assessment |
EM&A |
Environmental Monitoring & Audit |
EMIS |
Environmental Mitigation Implementation Schedule |
EP |
Environmental Permit |
EPD |
Environmental Protection Department |
EPSS |
Emergency Power Supply Systems |
ET |
Environmental Team |
FCZ |
Fish Culture Zone |
HKBCF |
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities |
HKIA |
Hong Kong International Airport |
HSF |
High Speed Ferry |
IEC |
Independent Environmental Checker |
LKC |
Lung Kwu Chau |
MMHK |
Mott MacDonald Hong Kong Limited |
MMWP |
Marine Mammal Watching Plan |
MSS |
Maritime Surveillance System |
MTRMP-CAV |
Updated Marine Travel Routes and Management Plan for Construction and Associated Vessel |
NEL |
Northeast Lantau |
NWL |
Northwest Lantau |
PAM |
Passive Acoustic Monitoring |
SC |
Sha Chau |
SCZ |
Speed Control Zone |
SCLKCMP |
Sha Chau and Lung Kwu Chau Marine Park |
SS |
Suspended Solids |
STG |
Encounter Rate of Number of Dolphin Sightings |
SWL |
Southwest Lantau |
T2 |
Terminal 2 |
The Manual |
The Updated EM&A Manual |
The Project |
The Expansion of Hong Kong International Airport into a Three-Runway System |
The SkyPier Plan |
Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier |
TSP |
Total Suspended Particulates |
WL |
West Lantau |
WMP |
Waste Management Plan |
The “Expansion of Hong Kong International Airport into a Three-Runway System” (the Project) serves to meet the future air traffic demands at Hong Kong International Airport (HKIA). On 7 November 2014, the Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) for the Project was approved and an Environmental Permit (EP) (Permit No.: EP-489/2014) was issued for the construction and operation of the Project.
Airport Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the Updated EM&A Manual (the Manual).
This is the 24th Construction Phase Quarterly EM&A Report for the Project which summarises the monitoring results and audit findings of the EM&A programme during the reporting period from 1 October 2021 to 31 December 2021.
Key Activities in the Reporting Period
EM&A Activities Conducted in the Reporting Period
The EM&A programme was undertaken in accordance with the Manual of the Project. Summary of the monitoring activities during this reporting period is presented as below:
Monitoring Activities |
Number of Sessions |
1-hour Total Suspended Particulates (TSP) air quality monitoring |
96 |
Noise monitoring |
52 |
Water quality monitoring |
37 |
Vessel line-transect surveys for Chinese White Dolphin (CWD) monitoring |
6 |
Land-based theodolite tracking survey effort for CWD monitoring |
6 |
Environmental auditing works, including weekly site inspections of construction works conducted by the ET and bi-weekly site inspections conducted by the Independent Environmental Checker (IEC), audit of SkyPier High Speed Ferries (HSF), audit of construction and associated vessels, and audit of implementation of Marine Mammal Watching Plan (MMWP) and Dolphin Exclusion Zone (DEZ) Plan, were conducted in the reporting period. Based on information including ET’s observations, records of Maritime Surveillance System (MSS), and contractors’ site records, it is noted that environmental pollution control and mitigation measures were properly implemented and construction activities of the Project in the reporting period did not introduce adverse impacts to the sensitive receivers.
In accordance with Section 6.2.1.1
of the Manual, the
methodology of annual sewage flow monitoring for the existing gravity sewer
from the airport discharge manhole to Tung Chung Sewage Pumping Station (TCSPS)
should be prepared and
submitted to EPD one year before the scheduled commencement of operation of the
proposed third runway. As such, the sewage flow monitoring methodology paper
was prepared, submitted and subsequently approved by EPD on 21 June 2021. The
annual sewage flow monitoring has also been started since June 2021. According
to the daily flow monitoring record of Sewage Pumping Station 1 (SPS-1) located
at the Airport from October to December 2021 (see Appendix
C), the daily average flow of 16,319 m3/day for October
2021, 15,717 m3/day for November 2021 and 14,866 m3/day
for December 2021 were well below 80% of pipe full flow capacity of 53,395.2 m3/day
as defined in Section 2.6.3 of the approved sewage flow monitoring methodology
paper. For the subsequent sets of sewage flow monitoring data for SPS-1, it
will be presented in upcoming Quarterly and Annual EM&A Reports.
Snapshots of Good Environmental Practices in the Reporting Period
|
|
|
Use of sandbags and water-filled barriers for muddy water discharge prevention |
Use of earth bund as speed cushion for dust suppression purpose |
Provision of environmental training for site personnel |
Key examples of good site practices implemented in the Project are highlighted as below:
1. Sandbags and water-filled barriers were placed along site boundary to prevent muddy water discharge to nearby swale.
2. Earth bund as speed cushion was set up at haul road to reduce vehicle speed and minimise the generation of fugitive dust.
3. Environmental training was provided to workers for proper waste management and chemical waste handling procedures.
Summary Findings of the EM&A Programme
The monitoring works for construction dust, construction noise, water quality, construction waste, landscape & visual, and CWD were conducted during the reporting period in accordance with the Manual.
Monitoring results of construction dust, construction noise, construction waste, and CWD monitoring did not trigger the corresponding Action and Limit Levels in the reporting period.
The water quality monitoring results for all parameters, except suspended solids (SS), obtained during the reporting period were within the corresponding Action and Limit Levels stipulated in the EM&A programme. Relevant investigation and follow-up actions will be conducted according to the EM&A programme if the corresponding Action and Limit Levels are triggered. For SS, some testing results triggered the relevant Action Levels, and the corresponding investigations were conducted accordingly. The investigation findings concluded that the cases were not related to the Project. To conclude, the construction activities in the reporting period did not introduce adverse impact to all water quality sensitive receivers.
The key findings of the EM&A programme during the reporting period are summarised as below:
|
Yes |
No |
Details |
Analysis / Recommendation / Remedial Actions |
Breach of Limit Level^ |
|
√ |
No breach of Limit Level was recorded. |
Nil |
Breach of Action Level^ |
|
√ |
No breach of Action Level was recorded. |
Nil |
Complaints Received |
√ |
|
A complaint regarding dust issue at 3RS construction site area was received on 6 October 2021. |
ET requested the relevant contractors to provide information related to the complaint. Regular site inspections and ad-hoc inspection were conducted in which no item related to insufficient water spraying was recorded. The contractors were reminded to continue implementing dust suppression measures, especially sufficient water spraying at the site area in accordance with the implementation schedule in the EM&A Manual. Hence, the case was considered closed. |
√ |
|
A complaint regarding dust issue at 3RS construction site area near northeastern quay bus station was received on 29 October 2021. |
ET requested the relevant contractor to provide information related to the complaint. Regular site inspections and ad-hoc inspection were conducted in which no item related to dust issue was recorded and water spraying at the concerned location was observed. All contractors were reminded to properly implement dust suppression measures, especially water spraying at their site area in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
√ |
|
A complaint regarding dust issue at 3RS construction site area was received on 7 November 2021. |
ET requested the relevant contractor to provide information related to the complaint. During a regular site inspection, dust was observed when there was vehicle movement on haul road, and was rectified by the contractor afterwards. An ad-hoc inspection was conducted in which water spraying at the concerned haul road was observed. All contractors were reminded to properly implement dust mitigation measures, especially water spraying on the haul road in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
√ |
|
Two emails regarding dust issue were received on 15 November 2021. |
ET requested the relevant contractor to provide information related to the complaint. During a regular site inspection, dust was observed when there was vehicle movement on haul road and was rectified by the contractor promptly. An ad-hoc inspection was conducted subsequently in which water spraying at the concerned haul road was observed. All contractors were reminded to properly implement dust mitigation measures, especially water spraying on the haul road in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
√ |
|
A complaint regarding Non-road Mobile Machinery (NRMM) issue at 3RS contractor’s works area was received on 24 November 2021. |
ET requested the relevant contractor to provide information related to the complaint. According to the information received, the contractor had obtained a valid NRMM label for the concerned vehicle. All contractors were reminded to continue and regular update their NRMM plant inventory list, to self-check and ensure proper NRMM labels are displayed on their on-site vehicles and machines. Hence, the case was considered closed. |
|
√ |
|
A complaint regarding suspected dump truck for garbage disposal that was not properly covered was received on 1 December 2021. |
ET requested the relevant contractors to provide information related to the complaint. Regular site inspections and ad-hoc inspection were conducted in which no item related to the covering of dump trucks was recorded. All contractors were reminded to ensure the proper covering of dump trucks for garbage disposal and avoid potential blowing away of materials during the process. Hence, the case was considered closed. |
|
√ |
|
A complaint regarding muddy water was received on 13 December 2021. |
ET requested the relevant contractor to provide information related to the complaint. Regular site inspections and ad-hoc inspections were conducted in which no observation on muddy water was recorded. All contractors were reminded to properly implement water quality mitigation measures on their work sites in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
Notification of any summons and status of prosecutions |
√ |
A contractor reported in October 2021 that they had pleaded guilty in court regarding a dust control emission incident for reclamation works in April 2021. |
Nil |
|
Changes that affect the EM&A |
|
√ |
There was no change to the construction works that may affect the EM&A. |
Nil |
Remarks:
^Only triggering of Action or Limit Level found related to Project works is counted as Breach of Action or Limit Level.
On 7 November 2014, the Environmental Impact Assessment (EIA) Report (Register No.: AEIAR-185/2014) for the “Expansion of Hong Kong International Airport into a Three-Runway System” (the Project) was approved and an Environmental Permit (EP) (Permit No.: EP-489/2014) was issued for the construction and operation of the Project.
Airport Authority Hong Kong (AAHK) commissioned Mott MacDonald Hong Kong Limited (MMHK) to undertake the role of Environmental Team (ET) for carrying out the Environmental Monitoring & Audit (EM&A) works during the construction phase of the Project in accordance with the Updated EM&A Manual (the Manual) submitted under EP Condition 3.1[1]. AECOM Asia Company Limited (AECOM) was employed by AAHK as the Independent Environmental Checker (IEC) for the Project.
The Project covers the expansion of the existing airport into a three-runway system (3RS) with key project components comprising land formation of about 650 ha and all associated facilities and infrastructure including taxiways, aprons, aircraft stands, a passenger concourse, an expanded Terminal 2, all related airside and landside works and associated ancillary and supporting facilities. The submarine aviation fuel pipelines and submarine power cables also require diversion as part of the works.
Construction of the Project is to proceed in the general order of diversion of the submarine aviation fuel pipelines, diversion of the submarine power cables, land formation, and construction of infrastructure, followed by construction of superstructures.
The summary of construction works programme can be referred to the corresponding Monthly EM&A Reports. Description of relevant contracts in the reporting period was presented in Appendix A of the Construction Phase Monthly EM&A Report No. 71.
This is the 24th Construction Phase Quarterly EM&A Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 1 October 2021 to 31 December 2021.
The Project’s organisation structure is provided in Appendix A. Contact details of the key personnel have been updated and provided in Table 1.1.
Table 1.1: Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Project Manager’s Representative (Airport Authority Hong Kong) |
Principal Manager, Environmental Compliance, Sustainability |
Lawrence Tsui |
2183 2734 |
Environmental Team (ET) (Mott MacDonald Hong Kong Limited) |
Environmental Team Leader |
Terence Kong |
2828 5919 |
Deputy Environmental Team Leader |
Heidi Yu |
2828 5704 |
|
Independent Environmental Checker (IEC) (AECOM Asia Company Limited) |
Independent Environmental Checker |
Jackel Law |
3922 9376
|
Deputy Independent Environmental Checker |
Roy Man |
3922 9141
|
Reclamation Works:
Party |
Position |
Name |
Telephone |
Contract 3206 Main Reclamation Works (ZHEC-CCCC-CDC Joint Venture) |
Project Manager |
Alan Mong |
3763 1352
|
Environmental Officer |
Zhang Bin Wang |
3763 1451 |
Airfield Works:
Party |
Position |
Name |
Telephone |
Contract 3301 North Runway Crossover Taxiway (FJT-CHEC-ZHEC Joint Venture) |
Deputy Project Director |
Kin Hang Chung |
9800 0048 |
Environmental Officer |
Joe Wong |
6182 0351 |
|
Contract 3302 Eastern Vehicular Tunnel Advance Works (China Road and Bridge Corporation) |
Project Manager |
Dickey Yau |
5699 4503 |
Environmental Officer |
Dennis Ho |
5645 0563 |
|
Contract 3303 Third Runway and Associated Works (SAPR Joint Venture) |
Project Manager |
Andrew Keung |
6277 6628 |
Environmental Officer |
Max Chin |
6447 5707 |
|
Contract 3305 Airfield Ground Lighting System (ADB Safegate Hong Kong Limited) |
Project Manager |
Allam Al-Turk |
2944 9725 |
Environmental Officer |
Calvin Sze |
9205 9277 |
|
Contract 3306 Observation Facility Control System Supporting Interim 2RS and 3RS (Chinney Alliance Engineering Limited) |
Project Director |
Dennis Yam |
9551 9920 |
Environmental Officer |
Richard Liu |
9216 8990 |
|
Contract 3307 Fire Training Facility (Paul Y. Construction Company Limited) |
Project Manager |
Chris Wong |
6110 1157 |
Environmental Officer
|
Albert Chan |
9700 1083 |
|
Contract 3308 Foreign Object Debris Detection System (DAS Aviation Services Group) |
Project Manager |
Jeffrey Yau |
9873 7422 |
Environmental Officer |
Terry Siu |
9141 2511 |
|
Contract 3310 North Runway Modification Works |
Project Manager |
Kingsley Chiang |
9424 8437 |
Environmental Officer |
Federick Wong |
9842 2703 |
Third Runway Concourse:
Party |
Position |
Name |
Telephone |
Contract 3402 New Integrated Airport Centres Enabling Works (Wing Hing Construction Co., Ltd.) |
Contract Manager |
Michael Kan |
9206 0550 |
Environmental Officer |
Lisa He |
5374 3418 |
|
Contract 3403 New Integrated Airport Centres Building and Civil Works (Sun Fook Kong Construction Limited) |
Project Manager |
Alice Leung |
9220 3162 |
Environmental Officer |
Ray Cheung |
9785 1566 |
|
Contract 3404 Integrated Airport Control System (Shun Hing Systems Integration Co., Ltd.) |
Project Manager |
Andy Ng |
9102 2739 |
Environmental Officer |
Richard Ng |
9802 9577 |
|
Contract 3405 Third Runway Concourse Foundation and Substructure Works (China Road and Bridge Corporation – Bachy Soletanche Group Limited – LT Sambo Co., Ltd. Joint Venture) |
Project Manager |
Francis Choi |
9423 3469 |
Environmental Officer |
Jacky Lai |
9028 8975 |
|
Contract 3408 Third Runway Concourse and Apron Works (Beijing Urban Construction Group Company Limited and Chevalier (Construction) Company Limited Joint Venture) |
Assistant Project Manager |
Qian Zhang |
5377 7976 |
Environmental Officer |
Malcolm Leung |
7073 7559 |
Terminal 2 (T2) Expansion:
Party |
Position |
Name |
Telephone |
Contract 3503 Terminal 2 Foundation and Substructure Works (Leighton – Chun Wo Joint Venture)
|
Project Manager |
Eric Wu |
3973 1718 |
Environmental Officer
|
Rex Yiu |
6465 6861 |
|
Contract 3508 Terminal 2 Expansion Works (Gammon Engineering & Construction Company Limited) |
Project Director |
Richard Ellis |
6201 5637 |
Environmental Officer |
Fanny Law |
6184 4650 |
Automated People Mover (APM) and Baggage Handling System (BHS):
Party |
Position |
Name |
Telephone |
Contract 3601 New Automated People Mover System (TRC Line) (CRRC Puzhen Bombardier Transportation Systems Limited and CRRC Nanjing Puzhen Co., Ltd. Joint Venture) |
Project Manager |
Hongdan Wei |
158 6180 9450 |
Environmental Officer
|
P L Wong
|
9143 2185 |
|
Contract 3602 Existing APM System Modification Works (Niigata Transys Co., Ltd.) |
Project Manager |
Kunihiro Tatecho |
9755 0351 |
Environmental Officer |
Carrie Kwan |
9276 0551 |
|
Contract 3603 3RS Baggage Handling System (VISH Consortium) |
Project Manager |
K C Ho |
9272 9626 |
Environmental Officer |
Eric Ha |
9215 3432 |
Construction Support (Facilities):
Party |
Position |
Name |
Telephone |
Contract 3721 Construction Support Infrastructure Works (China State Construction Engineering (Hong Kong) Ltd.) |
Site Agent |
Thomas Lui |
9011 5340 |
Environmental Officer |
Gary Yeung |
9042 1720 |
|
Contract 3722 Western Support Area – Construction Support Facilities (Tapbo Construction Company Limited and Konwo Modular House Limited Joint Venture) |
Deputy Project Director |
Philip Kong |
9337 8700 |
Environmental Officer |
Eddie Suen
|
6338 8862 |
|
Contract 3723 Eastern Support Area – Construction Support Facilities (Tapbo Construction Company Limited and Konwo Modular House Ltd. Joint Venture.) |
Deputy Project Director |
Philip Kong |
9337 8700 |
Environmental Officer |
Eddie Suen
|
6338 8862 |
|
Contract 3728 Minor Site Works (Shun Yuen Construction Company Limited) |
Contract Manager |
C K Liu |
9194 8739 |
Environmental Officer
|
K F Li |
9086 1793 |
|
Contract 3733 Emergency Repair Service (Wing Hing Construction Co., Ltd.)
|
Project Manager |
Michael Kan |
9206 0550 |
SHE Manager |
Mike Leung |
6625 2550 |
Airport Support Infrastructure:
Party |
Position |
Name |
Telephone |
Contract 3801 APM and BHS Tunnels on Existing Airport Island (China State Construction Engineering (Hong Kong) Ltd.) |
Project Manager |
Kingsley Chiang |
9424 8437 |
Environmental Officer |
Eunice Kwok |
9243 1331 |
|
Contract 3802 APM and BHS Tunnels and Related Works (Gammon Construction Limited) |
Project Director |
John Adams |
6111 6989 |
Environmental Officer |
Phoebe Ng |
9869 1105 |
Construction Support (Services / Licences):
Party |
Position |
Name |
Telephone |
Contract 3901A Concrete Batching Facility (K. Wah Concrete Company Limited) |
Project Manager |
Benedict Wong |
9553 2806 |
Environmental Officer |
C P Fung |
9874 2872 |
|
Contract 3901B Concrete Batching Facility (Gammon Construction Limited) |
Senior Project Manager |
Gabriel Chan |
2435 3260 |
Environmental Officer |
Rex Wong |
2695 6319 |
The contact information for the Project is provided in Table 1.2. The public can contact us through the following channels if they have any queries and comments on the environmental monitoring data and project related information.
Table 1.2: Contact Information of the Project
Channels |
Contact Information |
Hotline |
3908 0354 |
|
|
Fax |
3747 6050 |
Postal Address |
Airport Authority Hong Kong HKIA Tower 1 Sky Plaza Road Hong Kong International Airport Lantau Hong Kong Attn: Environmental Team Leader Mr Terence Kong c/o Mr Lawrence Tsui (TRD) |
The key activities of the Project carried out in the reporting period included reclamation works and land-based works. Works in the reclamation areas included marine filling, seawall and facilities construction, together with runway and associated works such as bored piling for approach lights. Land-based works on existing airport island involved mainly airfield works, foundation and substructure work for Terminal 2 expansion, modification and tunnel work for APM and BHS systems, and preparation work for utilities, with activities include site establishment, site office construction, road and drainage works, cable ducting, demolition of existing facilities, piling, and excavation works.
The locations of the key construction activities are presented in Figure 1.1. Figure 1.2 presents the latest layout of enhanced silt curtain deployed.
The status for all environmental aspects is presented in Table 1.3. The EM&A requirements remained unchanged during the reporting period.
Table 1.3: Summary of Status for All Environmental Aspects under the Updated EM&A Manual
Parameters |
EM&A Requirements |
Status |
Air Quality |
|
|
Baseline Monitoring |
At least 14 consecutive days before commencement of construction work |
The baseline air quality monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
At least 3 times every 6 days |
On-going |
Noise |
|
|
Baseline Monitoring |
Daily for a period of at least two weeks prior to the commencement of construction works |
The baseline noise monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
Weekly |
On-going |
Water Quality |
|
|
General Baseline Water Quality Monitoring for reclamation, water jetting and field joint works |
Three days per week, at mid-flood and mid-ebb tides, for at least four weeks prior to the commencement of marine works. |
The baseline water quality monitoring result has been reported in Baseline Water Quality Monitoring Report and submitted to EPD under EP Condition 3.4. |
General Impact Water Quality Monitoring for reclamation, water jetting and field joint works |
Three days per week, at mid-flood and mid-ebb tides. |
On-going for reclamation works. General impact water quality monitoring for water jetting works was completed on 23 May 2017. |
Initial Intensive Deep Cement Mixing (DCM) Water Quality Monitoring |
At least four weeks |
The Initial Intensive DCM Monitoring Report was submitted and approved by EPD in accordance with the Detailed Plan on DCM. |
Regular DCM Water Quality Monitoring |
Three times per week until completion of DCM works. |
Due to the completion of all marine-based DCM works within May 2021, regular DCM monitoring was ceased at all monitoring stations starting from 24 June 2021 and would be resumed if there are marine-based DCM works in the coming future. |
Sewerage and Sewage Treatment |
||
Methodology for carrying out annual sewage flow monitoring for concerned gravity sewer |
Methodology to be prepared and submitted to EPD one year before the scheduled commencement of operation of the proposed third runway. |
The proposed methodology of the annual sewage flow monitoring was approved by EPD. The annual flow monitoring has been started since June 2021. |
Details of the routine H2S monitoring system for the sewerage system of 3RS |
Details to be prepared and submitted to EPD at least one year before commencement of the operation of 3RS. |
The details of the routine H2S monitoring system will be prepared and submitted to EPD at least one year before commencement of operation of 3RS. |
Waste Management |
|
|
Waste Monitoring |
At least weekly |
On-going |
Land Contamination |
|
|
Supplementary Contamination Assessment Plan (CAP) |
At least 3 months before commencement of any soil remediation works. |
The Supplementary CAP was submitted and approved by EPD under EP condition 2.20. |
Contamination Assessment Report (CAR) for Golf Course |
CAR to be submitted for golf course |
The CAR for Golf Course was submitted and accepted by EPD. |
CAR for Terminal 2 Emergency Power Supply System |
CAR to be submitted for Terminal 2 Emergency Power Supply Systems
|
The CARs for Terminal 2 Emergency Power Supply Systems were submitted and accepted by EPD. |
Terrestrial Ecology |
|
|
Pre-construction Egretry Survey Plan |
Once per month in the breeding season between April and July, prior to the commencement of HDD drilling works. |
The Egretry Survey Plan was submitted and approved by EPD under EP Condition 2.14. |
Ecological Monitoring |
Monthly monitoring during the HDD construction works period from August to March. |
The terrestrial ecological monitoring at Sheung Sha Chau was completed in January 2019. |
Marine Ecology |
|
|
Pre-Construction Phase Coral Dive Survey |
Prior to marine construction works |
The Coral Translocation Plan was submitted and approved by EPD under EP Condition 2.12. |
Coral Translocation |
- |
The coral translocation was completed on 5 January 2017. |
Post-translocation Monitoring |
As per an enhanced monitoring programme based on the Coral Translocation Plan |
The post-translocation monitoring programme according to the Coral Translocation Plan was completed in April 2018. |
Chinese White Dolphins (CWD) |
|
|
Baseline Monitoring |
6 months of baseline surveys before the commencement of land formation related construction works. Vessel line transect surveys: Two full surveys per month; Land-based theodolite tracking surveys: Two days per month at the Sha Chau station and two days per month at the Lung Kwu Chau station; and Passive Acoustic Monitoring (PAM): For the whole duration of baseline period. |
Baseline CWD results were reported in the CWD Baseline Monitoring Report and submitted to EPD in accordance with EP Condition 3.4. |
Impact Monitoring |
Vessel line transect surveys: Two full surveys per month; Land-based theodolite tracking surveys: One day per month at the Sha Chau station and one day per month at the Lung Kwu Chau station; and PAM: For the whole duration for land formation related construction works. |
On-going
|
Landscape and Visual |
|
|
Landscape and Visual Plan |
At least 3 months before the commencement of construction works on the formed land of the Project. |
The Landscape & Visual Plan was submitted and approved by EPD under EP Condition 2.18 |
Baseline Monitoring |
One-off survey within the Project site boundary prior to commencement of any construction works |
The baseline landscape & visual monitoring result has been reported in Baseline Monitoring Report and submitted to EPD under EP Condition 3.4. |
Impact Monitoring |
Weekly
|
On-going |
Environmental Auditing |
|
|
Regular site inspection |
Weekly |
On-going |
Marine Mammal Watching Plan (MMWP) implementation measures |
Monitor and check |
On-going |
Dolphin Exclusion Zone (DEZ) Plan implementation measures |
Monitor and check |
On-going |
SkyPier High Speed Ferries (HSF) implementation measures |
Monitor and check |
On-going |
Construction and Associated Vessels implementation measures |
Monitor and check |
On-going |
Silt Curtain Deployment Plan implementation measures |
Monitor and check |
On-going |
Spill Response Plan implementation measures |
Monitor and check |
On-going |
Complaint Hotline and Email Channel |
Construction phase |
On-going |
Environmental Log Book |
Construction phase |
On-going |
Taking into account the construction works in the reporting period, impact monitoring of air quality, noise, water quality, waste management, landscape & visual, and CWD were carried out in the reporting period.
The EM&A programme also involved weekly site inspections and related auditing conducted by ET for the checking of implementation of required environmental mitigation measures recommended in the approved EIA Report. To promote the environmental awareness and enhance the environmental performance of the contractors, environmental trainings and regular environmental management meetings were conducted during the reporting period which are summarised as below:
● Six skipper trainings provided by ET; and
● Fifty-four environmental management meetings for EM&A review with works contracts.
The EM&A programme has been following the recommendations presented in the approved EIA Report and the Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix B.
Impact 1-hour Total Suspended Particulates (TSP) monitoring was conducted three times every six days at two representative monitoring stations during the reporting period. The locations of monitoring stations are described in Table 2.1 and presented in Figure 2.1.
The Action and Limit Levels of the air quality monitoring stipulated in the EM&A programme for triggering the relevant investigation and follow-up procedures under the programme are provided in Table 2.1 for reference.
Table 2.1: Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AR1A |
Man Tung Road Park |
306 |
500 |
AR2 |
Village House at Tin Sum |
298 |
The air quality monitoring results in the reporting period are summarised in Table 2.2 and the graphical plot is presented in Appendix C.
Table 2.2: Percentage of Air Quality Monitoring Results within Action and Limit Levels
|
AR1A |
AR2 |
Oct 2021 |
100% |
100% |
Nov 2021 |
100% |
100% |
Dec 2021 |
100% |
100% |
Overall |
100% |
100% |
Note: The percentages are calculated by dividing the number of monitoring results within their corresponding Action and Limit Levels by the total number of monitoring results. |
All monitoring results were within their corresponding Action and Limit Levels at all monitoring stations in the reporting period.
General meteorological conditions in the last month of the previous quarter and this reporting period were recorded and summarised in Table 2.3.
Table 2.3: General Meteorological Condition during Impact Air Quality Monitoring
|
Weather |
Dominant Wind Direction |
Sep 2021 |
Sunny to Cloudy |
Southwest |
Oct 2021 |
Sunny |
Southwest |
Nov 2021 |
Sunny to Fine |
Northwest |
Dec 2021 |
Sunny to Overcast |
Northwest |
No dust emission source was observed at the monitoring stations during the monitoring sessions. As the sensitive receivers were far away from the construction activities, with the implementation of dust control measures, there was no adverse impact at the sensitive receivers attributable to the works of the Project.
Impact noise monitoring was conducted at four representative monitoring stations once per week during 0700 and 1900 in the reporting period. The locations of monitoring stations are described in Table 2.4 and presented in Figure 2.1.
The Action and Limit Levels of the noise monitoring stipulated in the EM&A programme for triggering the relevant investigation and follow-up procedures under the programme are provided in Table 2.4 for reference.
Table 2.4: Impact Noise Monitoring Stations
Monitoring Station |
Location |
Action Level |
Limit Level |
NM1A |
Man Tung Road Park |
When one documented complaint is received from any one of the sensitive receivers |
75 dB(A) |
NM4 |
Ching Chung Hau Po Woon Primary School |
65dB(A) / 70 dB(A) (i) |
|
NM5 |
Village House in Tin Sum |
75 dB(A) |
|
NM6 |
House No. 1, Sha Lo Wan |
75 dB(A) |
|
Note: (i) The Limit Level for NM4 is reduced to 70dB(A) for being an educational institution. During school examination period, the Limit Level is further reduced to 65dB(A). |
The noise monitoring results in the reporting period are summarised in Table 2.5 and the graphical plot is presented in Appendix C.
Table 2.5: Percentage of Noise Monitoring Results within Action and Limit Levels
|
NM1A |
NM4 |
NM5 |
NM6 |
Oct 2021 |
100% |
100% |
100% |
100% |
Nov 2021 |
100% |
100% |
100% |
100% |
Dec 2021 |
100% |
100% |
100% |
100% |
Overall |
100% |
100% |
100% |
100% |
Note: The percentages are calculated by dividing the number of monitoring results within their corresponding Action and Limit Levels by the total number of monitoring results. |
No complaints were received from any sensitive receiver that triggered the Action Level.
General meteorological conditions in the last month of the previous quarter and this reporting period were recorded and summarised in Table 2.6.
Table 2.6: General Meteorological Condition during Impact Noise Monitoring
|
Weather |
Sep 2021 |
Sunny to Cloudy |
Oct 2021 |
Sunny to Cloudy |
Nov 2021 |
Sunny to Overcast |
Dec 2021 |
Sunny to Drizzle |
Major sources of noise dominating the monitoring stations observed during the construction noise impact monitoring were traffic noise near NM1A, school activities at NM4 and aircraft noise near NM5 and NM6. As the sensitive receivers were far away from the construction activities, with the implementation of noise control measures, there was no adverse impact at the sensitive receivers attributable to the works of the Project.
During the reporting period, water quality monitoring was conducted three days per week, at mid-flood and mid-ebb tides, at a total of 23 water quality monitoring stations, comprising 12 impact (IM) stations, 8 sensitive receiver (SR) stations, and 3 control (C) stations in the vicinity of the water quality sensitive receivers around the existing airport island in accordance with the Manual. The purpose of water quality monitoring at the IM stations is to promptly capture any potential water quality impacts from the Project before the impacts could become apparent at sensitive receivers (represented by the SR stations). Table 2.7 describes the details of the monitoring stations. Figure 2.2 shows the locations of the monitoring stations.
Table 2.7: Monitoring Locations and Parameters for Impact Water Quality Monitoring
Description |
Coordinates Easting Northing |
Parameters |
||
|
|
|||
C1 |
Control Station |
804247 |
815620 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
|
C2 |
Control Station |
806945 |
825682 |
|
C3(2) |
Control Station |
817803 |
822109 |
|
IM1 |
Impact Station |
807132 |
817949 |
|
IM2 |
Impact Station |
806166 |
818163 |
|
IM3 |
Impact Station |
805594 |
818784 |
|
IM4 |
Impact Station |
804607 |
819725 |
|
IM5 |
Impact Station |
804867 |
820735 |
|
IM6 |
Impact Station |
805828 |
821060 |
|
IM7 |
Impact Station |
806835 |
821349 |
|
IM8 |
Impact Station |
808140 |
821830 |
|
IM9 |
Impact Station |
808811 |
822094 |
|
IM10 |
Impact Station |
809794 |
822385 |
|
IM11 |
Impact Station |
811460 |
822057 |
|
IM12 |
Impact Station |
812046 |
821459 |
|
SR1A(1) |
Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) Seawater Intake for cooling |
812660
|
819977 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS |
SR2(2) |
Planned marine park / hard corals at The Brothers / Tai Mo To |
814166 |
821463 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
|
SR3 |
Sha Chau and Lung Kwu Chau Marine Park / fishing and spawning grounds in North Lantau |
807571 |
822147 |
General Parameters DO, pH, Temperature, Salinity, Turbidity, SS
|
SR4A |
Sha Lo Wan |
807810 |
817189 |
|
SR5A |
San Tau Beach SSSI |
810696 |
816593 |
|
SR6A(3) |
Tai Ho Bay, Near Tai Ho Stream SSSI |
814739 |
817963 |
|
SR7 |
Ma Wan Fish Culture Zone (FCZ) |
823742 |
823636 |
|
SR8(4) |
Seawater Intake for cooling at Hong Kong International Airport (East) |
811623 |
820390 |
Notes:
(1) With the operation of HKBCF, water quality monitoring at SR1A station was commenced on 25 October 2018.
(2) According to the Baseline Water Quality Monitoring Report, C3 station is not adequately representative as a control station of impact/ SR stations during the flood tide. The control reference has been changed from C3 to SR2 from 1 September 2016 onwards.
(3) As the access to SR6 was obstructed by the construction activities and temporary structures for Tung Chung New Town Extension, the monitoring location has been relocated to SR6A starting from 8 August 2019.
(4) The monitoring location for SR8 is subject to further changes due to silt curtain arrangements and the progressive relocation of this seawater intake.
The Action and Limit Levels for general water quality monitoring stipulated in the EM&A programme for triggering the relevant investigation and follow-up procedures under the programme are presented in Table 2.8. The control and IM stations during flood tide and ebb tide for general water quality monitoring are presented in Table 2.9.
Table 2.8: Action and Limit Levels for General Water Quality Monitoring
Parameters |
Action Level |
Limit Level |
||
Action and Limit Levels for general water quality monitoring (excluding SR1A & SR8) |
||||
DO in mg/l (Surface, Middle & Bottom) |
Surface and Middle 4.5 mg/l |
Surface and Middle 4.1 mg/l 5 mg/l for Fish Culture Zone (SR7) only |
||
Bottom 3.4 mg/l |
Bottom 2.7 mg/l |
|||
SS in mg/l |
23 |
or 120% of upstream control station at the same tide of the same day, whichever is higher |
37 |
or 130% of upstream control station at the same tide of the same day, whichever is higher |
Turbidity in NTU |
22.6 |
36.1 |
||
Action and Limit Levels SR1A |
|
|
|
|
SS (mg/l) |
33 |
42 |
||
Action and Limit Levels SR8 |
|
|
|
|
SS (mg/l) |
52 |
|
60 |
|
Notes:
1. For DO measurement, Action or Limit Level is triggered when monitoring result is lower than the limits.
2. For parameters other than DO, Action or Limit Level of water quality results is triggered when monitoring results is higher than the limits.
3. Depth-averaged results are used unless specified otherwise.
4. In view of the construction programme for marine-based DCM works, regular DCM monitoring was ceased since 24 June 2021 and will be resumed starting from 11 January 2022 in view of the upcoming marine-based DCM works.
Table 2.9: The Control and Impact Stations during Flood Tide and Ebb Tide for General Water Quality Monitoring
Control Station |
Impact Stations |
Flood Tide |
|
C1 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, SR3 |
SR21 |
IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR3, SR4A, SR5A, SR6A, SR8 |
Ebb Tide |
|
C1 |
SR4A, SR5A, SR6A |
C2 |
IM1, IM2, IM3, IM4, IM5, IM6, IM7, IM8, IM9, IM10, IM11, IM12, SR1A, SR2, SR3, SR7, SR8 |
Note:
1. As per findings of Baseline Water Quality Monitoring Report, the control reference has been changed from C3 to SR2 from 1 Sep 2016 onwards.
The summary or results within their corresponding Action and Limit Levels in the reporting period are presented in Table 2.10. The weather and sea conditions in the last month of the previous quarter and this reporting period were recorded and summarised in Table 2.11.
Table 2.10: Percentage of Water Quality Monitoring Results within Action and Limit Levels
General Water Quality Monitoring |
||||
DO (Surface and Middle) |
DO (Bottom) |
SS |
Turbidity |
|
Oct 2021 |
100% (367/367) |
100% (367/367) |
98.5% (403/409) |
100% (367/367) |
Nov 2021 |
100% (455/455) |
100% (455/455) |
99.8% (506/507) |
100% (455/455) |
Dec 2021 |
100% (455/455) |
100% (455/455) |
99.8% (506/507) |
100% (455/455) |
Overall |
100% |
100% |
99.4% |
100% |
Note: (1) The percentages are calculated by dividing the number of depth-averaged results complying with their corresponding Action and Limit Levels by the total number of depth-averaged results. (2) The number in the bracket under the percentage represents the total number of depth-averaged results complying with their corresponding Action and Limit Levels over the total number of depth-averaged results. |
Table 2.11: General Weather Condition and Sea Condition during Impact Water Quality Monitoring
|
Weather |
Sea Condition |
Sep 2021 |
Sunny to Rainy |
Calm to Rough |
Oct 2021 |
Sunny to Rainy |
Calm to Rough |
Nov 2021 |
Sunny to Cloudy |
Calm to Rough |
Dec 2021 |
Sunny to Rainy |
Calm to Rough |
The monitoring results for all parameters, except suspended solid (SS), obtained during the reporting period were within their corresponding Action and Limit Levels stipulated in the EM&A programme. The detailed monitoring results are presented in Appendix C. Relevant investigation and follow-up actions will be conducted according to the EM&A programme if the corresponding Action and Limit Levels are triggered.
For SS, some of the testing results triggered the corresponding Action Levels in the reporting period, and investigations were conducted accordingly. Summaries of results triggering Action Levels for SS are presented in Table 2.12 to Table 2.13.
Details of the investigation findings were presented in Construction Phase Monthly EM&A Report Nos. 70, 71 and 72, which concluded that all results triggering the Action Levels were not related to the Project.
Table 2.12: Summary of SS Compliance Status (Mid-Ebb Tide)
IM1 |
IM2 |
IM3 |
IM4 |
IM5 |
IM6 |
IM7 |
IM8 |
IM9 |
IM10 |
IM11 |
IM12 |
SR1A |
SR2 |
SR3 |
SR4A |
SR5A |
SR6A |
SR7 |
SR8 |
|
23/10/2021 |
|
|
D |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
11/11/2021 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
No. of result triggering Action or Limit Level |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Table 2.13: Summary of SS Compliance Status (Mid-Flood Tide)
IM1 |
IM2 |
IM3 |
IM4 |
IM5 |
IM6 |
IM7 |
IM8 |
IM9 |
IM10 |
IM11 |
IM12 |
SR1A |
SR3 |
SR4A |
SR5A |
SR6A |
SR7 |
SR8 |
|
07/10/2021 |
|
|
|
|
|
|
|
D |
|
|
|
|
|
|
|
|
|
|
|
23/10/2021 |
|
|
|
|
D |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
23/12/2021 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
No. of result triggering Action or Limit Level |
0 |
1 |
1 |
1 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
Note: The monitoring results compiled with their corresponding Action or Limit Levels are presented in Appendix C.
Legend: |
|
|
Result within corresponding Action and Limit Levels |
|
Result triggered the Action Level at monitoring station located upstream of the Project based on dominant tidal flow |
D |
Result triggered the Action Level at monitoring station located downstream of the Project based on dominant tidal flow |
|
Upstream station with respect to the Project during the respective tide based on dominant tidal flow |
|
Downstream station with respect to the Project during the respective tide based on dominant tidal flow |
During the reporting period, it is noted that most of the monitoring results were within their corresponding Action and Limit Levels, while some results triggered the corresponding Action Levels, and investigations were conducted accordingly. Based on the findings presented in Construction Phase Monthly EM&A Report Nos. 70, 71 and 72, the cases that triggered the corresponding Action Levels were not related to the Project. Hence, the Project did not introduce adverse impact to all water quality sensitive receivers. All required actions under the Event and Action Plan were followed.
Nevertheless, the non-project related trigger was attended to and initiated corresponding action and measures. As part of the EM&A programme, the construction methods and mitigation measures for water quality will continue to be monitored and opportunities for further enhancement will continue to be explored and implemented where possible, to strive for better protection of water quality and the marine environment.
In the meantime, the contractors were reminded to implement and maintain all mitigation measures during weekly site inspections and regular environmental management meetings. These include maintaining mitigation measures properly for reclamation works including marine filling and seawall construction as recommended in the Manual.
In accordance with the Manual, waste generated from construction activities was audited once per week to determine if wastes were being managed in accordance with the Waste Management Plan (WMP) prepared for the Project, contract-specific WMP, and any statutory and contractual requirements. All aspects of waste management including waste generation, storage, transportation, and disposal were assessed during the audits.
The Action and Limit Levels of the construction waste are provided in Table 2.14.
Table 2.14: Action and Limit Levels for Construction Waste
Monitoring Stations |
Action Level |
Limit Level |
Construction Area |
When one valid documented complaint is received |
Non-compliance of the WMP, contract-specific WMPs, any statutory and contractual requirements |
Weekly monitoring of the Project construction works was carried out by the ET in the reporting period to check and monitor the implementation of proper waste management practices.
Recommendations made by the ET included provision and maintenance of proper chemical waste storage area, as well as handling, segregation, and regular disposal of general refuse. The contractors had taken actions to implement the recommended measures. Waste management audits were carried out by ET according to the requirement of the Waste Management Plan, Updated EM&A Manual and the implementation schedule of the waste management mitigation measures in Appendix B.
Based on updated contractors’ information, summary of construction waste generated in the reporting period is presented in Table 2.15. Proactive measures have been undertaken during the re-configuration of T2 building. The contractor has established the recycling strategy for C&D materials with proper planning and design to maximize recycling and reuse. Dedicated recyclers were employed for different kinds of recyclable materials by the contractor, and ET and IEC have carried out site visits to recyclers’ facilities to review recycling process. Dedicated areas for sorting of materials are established on site. Recyclable materials such as steel, reinforcement bar, structural steel, aluminium, copper, other metals and glass are sorted on-site and transported off-site for recycling. ET and IEC have carried out site audits regularly and reviewed the trip ticket system.
Table 2.15: Construction Waste Statistics
|
C&D(1) Material Stockpiled for Reuse or Recycle (m3) |
C&D Material Reused in the Project (m3) |
C&D Material Reused in other Projects (m3) |
C&D Material Transferred to Public Fill(3) (m3) |
Chemical Waste (kg) |
Chemical Waste (l) |
General Refuse (tonne) |
Oct 2021(2) |
8,018 |
20,471 |
24,211 |
3,896 |
30 |
3,400 |
1,744 |
Nov 2021(2) |
16,540 |
6,051 |
7,039 |
5,493 |
0 |
1,400 |
2,631 |
Dec 2021(2) |
4,842 |
15,538 |
1,251 |
10,204 |
600 |
2,742 |
2.764 |
Total |
29,400 |
42,060 |
32,501 |
19,593 |
630 |
7,542 |
7,139 |
Notes: 1. C&D refers to Construction and Demolition. 2. Paper, metals and/or plastics were recycled in the reporting period. 3. C&D materials not suitable for reuse on-site, including asphalt waste and sediment slurry, were transferred to public fill during the reporting period. |
There were no complaints, non-compliance of the WMP, contract-specific WMPs, statutory and contractual requirements that triggered Action and Limit Levels in the reporting period.
Marine sediment is managed according to the EIA Report, Updated EM&A Manual and Waste Management Plan of the Project. The sampling process, storage conditions of the excavated marine sediment, treatment process, final backfilling location as well as associated records were inspected and checked by ET and verified by IEC to ensure they were in compliance with the requirements as stipulated in the Waste Management Plan.
Sampling works for marine sediment generated from the reclaimed land area was on-going during the reporting period. The details of the marine sediment sampling, treatment and backfilling will be reported in the subsequent EM&A Reports upon completion.
CWD monitoring was conducted by vessel line transect survey at a frequency of two full surveys per month, supplemented by land-based theodolite tracking survey and PAM. The frequency of the land-based theodolite tracking survey during the construction phase was one day per month at both Sha Chau (SC) and Lung Kwu Chau (LKC) stations, as stipulated in the Manual. The vessel survey transects followed the transect lines proposed in the Manual and are consistent with those used in the Agriculture, Fisheries and Conservation Department (AFCD) long-term CWD monitoring programme. The transect locations of CWD monitoring by vessel line transect survey conducted from October to December 2021 are shown in Figure 2.3, whilst the land-based theodolite tracking survey stations are described in Table 2.16 and depicted in Figure 2.4. The location of the PAM device is shown in Figure 2.10.
Table 2.16: Land-based Theodolite Tracking Survey Station Details
Stations |
Location |
Geographical Coordinates |
Station Height (m) |
Approximate Tracking Distance (km) |
D |
Sha Chau (SC) |
22° 20’ 43.5” N 113° 53’ 24.66” E |
45.66 |
2 |
E |
Lung Kwu Chau (LKC) |
22° 22’ 44.83” N 113° 53’ 0.2” E |
70.40 |
3 |
The Action Level and Limit Level for CWD monitoring were formulated by an action response approach using the running quarterly dolphin encounter rates (STG and ANI) derived from baseline monitoring data, as presented in the CWD Baseline Monitoring Report. The derived values of Action and Limit Levels for CWD monitoring are shown in Table 2.17.
Table 2.17: Derived Values of Action Level and Limit Level for Chinese White Dolphin Monitoring
|
NEL, NWL, AW, WL and SWL as a Whole |
Action Level |
Running quarterly STG < 1.86 & ANI < 9.35 |
Limit Level |
Two consecutive running quarterly (3-month) STG < 1.86 & ANI < 9.35 |
Survey Effort
During the October to December 2021 reporting period, a total of six sets of vessel line transect survey covering all transects in Northeast Lantau (NEL), Northwest Lantau (NWL), Airport West (AW), West Lantau (WL) and Southwest Lantau (SWL) survey areas were conducted at a frequency of twice per month, in each survey area.
A total of around 1,357 km of survey effort was collected from these surveys, with around 80.9% of the total survey effort being conducted under favourable weather condition (i.e. Beaufort Sea State 3 or below with favourable visibility). Details of the survey effort data are presented in Appendix C.
CWD Sighting
From October to December 2021, there were a total of 29 sightings of CWD, with 91 dolphins sighted (Table 2.18). Amongst these sightings, 27 sightings with 89 dolphins were recorded during on-effort searches under favourable weather condition.
When breaking down the sightings by survey areas, one sighting with one dolphin, 22 sightings with 70 dolphins and 6 sightings with 20 dolphins were recorded in NWL, WL and SWL respectively during the current reporting period. No CWD was sighted on AW transect nor in NEL survey area.
Compared with the last quarter (i.e. July to September 2021), both the total number of CWD sightings and total number of the dolphins decreased by 43% and 45% respectively. The most noticeable decrease was reflected from the NWL survey area.
Compared with the same quarter of last year (i.e. October to December 2020), there were decreases in both the total number of sightings and the total number of dolphins by 36% and 34% respectively. Such decreases were recorded throughout the three survey areas.
Table 2.18 below shows the comparison of the numbers of sightings and dolphins amongst the current reporting period, last quarter, and the same quarter of last year.
Table 2.18: Summary of Number of CWD Sightings and Number of Dolphins for the Same Quarter Last Year, Previous Quarter, and Current Reporting Period
|
Same Quarter of Last Year |
Previous Reporting Period |
Current Reporting Period |
|
October to December 2020 |
July to September 2021 |
October to December 2021 |
NEL |
0 (0) |
0 (0) |
0 (0) |
NWL |
2 (2) |
9 (20) |
1 (1) |
AW |
2 (4) |
0 (0) |
0 (0) |
WL |
27 (88) |
29 (105) |
22 (70) |
SWL |
14 (43) |
13 (39) |
6 (20) |
Total |
45 (137) |
51 (164) |
29 (91) |
Note: Values in ( ) represent number of dolphins
The distribution of CWD sightings recorded from October to December 2021 is illustrated in Figure 2.5. In NWL, there was only one CWD sighting recorded near Lung Kwu Chau. In WL, CWD sightings were scattered amongst the survey area from Tai O to Peaked Hill. In SWL, CWD sightings were scattered in the waters around Fan Lau and in the central part of the survey area. No CWD sightings were recorded in NEL survey area during the reporting period. Details of the sighting data are presented in Appendix C.
Figure 2.5: Sightings Distribution of Chinese White Dolphins from October to December 2021
Remarks: (1) Please note that there are 29 pink circles on
the map indicating the sighting locations of CWD. Some of them were very close
to each other and therefore appear overlapped on this sighting distribution
map. (2) Marine park excludes land area and the
landward boundary generally follows the high water mark along the coastline.
Encounter Rate
The dolphin encounter rates for the number of on-effort dolphin sightings per 100 km survey effort (STG) and for the total on-effort number of dolphins per 100 km survey effort (ANI) in the whole survey area (i.e. NEL, NWL, AW, WL and SWL) for October, November and December 2021 are summarised in Table 2.19.
In this reporting period, both the running quarterly STG and ANI increased from October to November 2021 but followed by a drop in December 2021. This is mainly resulted from the drops for the monthly STG and ANI from October to December 2021 (STG: from 3.71 to 1.59; ANI: from 11.42 to 4.51). No Action Level for CWD monitoring was triggered during the reporting period.
Compared with the previous reporting period (i.e. July to September 2021), both the running quarterly STG and ANI decreased from September 2021 to December 2021 (STG: from 3.84 to 2.46; ANI from 12.38 to 8.11). While comparing with the same quarter of last year (i.e. October to December 2020), both the running quarterly STG and ANI decreased, from 3.71 to 2.46 and from 11.64 to 8.11 respectively. Encounter rates for these periods are summarised in Table 2.19 and graphical presentation is provided in Appendix C.
Table 2.19: Summary of Monthly and Running Quarterly STG and ANI of Chinese White Dolphin for the Same Quarter Last Year, Previous Quarter, and Current Reporting Period
|
Same Quarter of Last Year |
Previous Reporting Period |
Current Reporting Period |
||||||
|
Oct 20 |
Nov 20 |
Dec 20 |
Jul 21 |
Aug 21 |
Sep 21 |
Oct 21 |
Nov 21 |
Dec 21 |
Monthly STG |
3.89 |
3.30 |
3.99 |
6.84 |
1.32 |
3.55 |
3.71 |
2.16 |
1.59 |
Monthly ANI |
17.80 |
10.37 |
7.19 |
21.22 |
4.19 |
12.29 |
11.42 |
8.63 |
4.51 |
Running Quarterly STG |
2.24 |
2.73 |
3.71 |
4.39 |
3.69 |
3.84 |
2.77 |
3.15 |
2.46 |
Running Quarterly ANI |
9.54 |
10.52 |
11.64 |
12.98 |
11.32 |
12.38 |
9.05 |
10.84 |
8.11 |
Note: For detailed calculations of encounter rates STG and ANI for the current reporting period, please refer to the Construction Phase Monthly EM&A Report Nos. 70, 71, and 72.
Group Size
Between October and December 2021, the group size of CWD sightings ranged from 1 to 13 dolphins. The average group size of CWD was 3.14 dolphins per group, which is slightly smaller than that of the last quarter (3.22 dolphins per group). The average group size of CWD in this reporting quarter is slightly larger than that of the same quarter of last year (3.0 dolphins per group).
In this reporting quarter, the numbers of CWD sightings with small group size (i.e. 1-2 dolphins) and medium group size (i.e. 3-9 dolphins) were similar. There are no observable differences in the distribution pattern between small-sized and medium-sized dolphin groups in WL and SWL as they all scattered amongst survey areas. In NWL, there was only one small-sized dolphin group recorded near Lung Kwu Chau during the current reporting period.
One CWD sighting with large group size (i.e. 10 or more dolphins) was recorded in this reporting period, which was encountered in WL survey area near the offshore waters between Yi O and Peaked Hill. Sighting locations of CWD groups with different group sizes are depicted in Figure 2.6.
Figure 2.6: Sighting Locations of Chinese White Dolphins with Different Group Sizes
Remarks: (1) Please note that there are
29 circles on the map indicating the sighting locations of CWD. Some of them
were very close to each other and therefore appear overlapped on this sighting
distribution map. (2) Marine park excludes land area
and the landward boundary generally follows the high water mark along the coastline.
Activities and Association with Fishing Boats
From October to December 2021, 14 sightings of CWD were recorded with feeding activities. Amongst them, two sightings were observed associated with operating shrimp trawler in WL and gillnetter in SWL survey area.
The number of sightings with feeding recorded in the current reporting period is same as that in the previous reporting period (i.e. 14 sightings involved feeding activities between July and September 2021). The number of CWD sightings with feeding activities in this reporting period is much higher than that in the same quarter of last year (i.e. 4 sightings between October to December 2020).
The sighting locations of CWDs engaged in different behaviours during the current reporting period are illustrated in Figure 2.7.
Figure 2.7: Sighting Locations of Chinese White Dolphins Engaged in Different Behaviours
Remarks: Marine park excludes land area and the landward boundary generally follows the high water mark along the coastline.
Mother-calf Pairs
From October to December 2021, six sightings of CWD were recorded with the presence of mother-and-unspotted juvenile pairs and/or mother-and-unspotted calf pairs observed, which is similar to that recorded in the previous reporting quarter (i.e. seven sightings between July and September 2021) as well as that recorded in the same quarter of last year (i.e. seven sightings between October to December 2020). These six sightings were recorded in WL and SWL.
The locations of CWD sightings with the presence of mother-calf pairs are shown in Figure 2.8.
Figure 2.8: Sighting Locations of Mother-calf Pairs
Remarks: (1) Please note that there are six circles on
the map indicating the sighting locations of Mother-Calf pair. (2) Marine park excludes land area and the landward boundary
generally follows the high water mark along the coastline.
Photo Identification
Between October and December 2021, a total number of 31 different CWD individuals were identified altogether for 46 times. Re-sighting information of CWD individuals provides an initial idea of their range use and apparent connection between different areas of Lantau waters. Amongst these 31 different CWD individuals, eight animals (i.e. SLMM003, SLMM012, SLMM014, SLMM025, SLMM037, WLMM043, WLMM071 and WLMM079) were sighted for more than once.
Five individuals including SLMM003, SLMM012, SLMM025, SLMM037 and WLMM079 were re-sighted in different survey areas (i.e. WL and SWL) during this reporting period. The most frequently re-sighted individuals in this reporting quarter are SLMM003, SLMM037 and WLMM043 that each of them has been encountered four times. The number of CWD individuals re-sighted more than once and the number of CWD individuals showing cross-area movement in the current reporting period are both lower than those of the previous reporting quarter from July to September 2021 (26 and 14 individuals respectively).
A summary of photo identification works is presented in Table 2.20. Representative photos of the 31 identified individuals and figures depicting the sighting locations of the aforementioned eight re-sighted individuals recorded in this reporting period are presented in Appendix C.
Table 2.20: Summary of Photo Identification
Individual ID |
Date of sighting |
Sighting Group No. |
Area |
|
Individual |
Date of sighting |
Sighting Group No. |
Area |
NLMM016 |
07-Dec-21 |
1 |
NWL |
|
SLMM058 |
04-Nov-21 |
2 |
WL |
NLMM081 |
06-Oct-21 |
4 |
WL |
|
SLMM066 |
04-Nov-21 |
4 |
WL |
SLMM003 |
06-Oct-21 |
6 |
WL |
|
WLMM001 |
11-Nov-21 |
1 |
SWL |
|
04-Nov-21 |
3 |
WL |
|
WLMM003 |
04-Nov-21 |
1 |
WL |
|
11-Nov-21 |
1 |
SWL |
|
WLMM007 |
06-Oct-21 |
4 |
WL |
|
06-Dec-21 |
2 |
SWL |
|
WLMM040 |
06-Dec-21 |
2 |
SWL |
SLMM007 |
06-Oct-21 |
4 |
WL |
|
WLMM043 |
06-Oct-21 |
1 |
WL |
SLMM010 |
04-Nov-21 |
3 |
WL |
|
|
03-Nov-21 |
1 |
WL |
SLMM012 |
04-Nov-21 |
5 |
WL |
|
|
04-Nov-21 |
1 |
WL |
|
16-Dec-21 |
1 |
SWL |
|
|
15-Dec-21 |
1 |
WL |
SLMM014 |
11-Nov-21 |
1 |
SWL |
|
WLMM062 |
06-Oct-21 |
4 |
WL |
|
16-Dec-21 |
1 |
SWL |
|
WLMM068 |
15-Dec-21 |
1 |
WL |
SLMM025 |
06-Oct-21 |
4 |
WL |
|
WLMM071 |
06-Oct-21 |
2 |
WL |
|
16-Dec-21 |
1 |
SWL |
|
|
04-Nov-21 |
2 |
WL |
SLMM027 |
04-Nov-21 |
5 |
WL |
|
WLMM079 |
06-Oct-21 |
6 |
WL |
SLMM030 |
19-Oct-21 |
2 |
WL |
|
|
04-Nov-21 |
3 |
WL |
SLMM031 |
27-Oct-21 |
3 |
SWL |
|
|
11-Nov-21 |
1 |
SWL |
SLMM037 |
06-Oct-21 |
6 |
WL |
|
WLMM114 |
04-Nov-21 |
3 |
WL |
|
04-Nov-21 |
3 |
WL |
|
WLMM131 |
11-Nov-21 |
1 |
SWL |
|
|
5 |
WL |
|
WLMM149 |
04-Nov-21 |
2 |
WL |
|
06-Dec-21 |
2 |
SWL |
|
WLMM168 |
06-Oct-21 |
2 |
WL |
SLMM049 |
06-Oct-21 |
4 |
WL |
|
WLMM169 |
06-Oct-21 |
4 |
WL |
SLMM052 |
06-Oct-21 |
4 |
WL |
|
WLMM170 |
06-Oct-21 |
4 |
WL |
Survey Effort
Between October and December 2021, a total of six days of land-based theodolite tracking survey effort were completed, including three days on Lung Kwu Chau and three days on Sha Chau. In total, eight CWD groups were tracked from the Lung Kwu Chau station while no CWD groups were tracked from the Sha Chau station, with an overall 0.22 CWD groups sighted per survey hour.
Information on survey effort and CWD groups sighted during land-based theodolite tracking surveys are presented in Table 2.21. Details on the survey effort and CWD groups tracked are presented in Appendix C. The first sighting locations of CWD groups tracked between October and December 2021 are shown in Figure 2.9.
Table 2.21: Summary of Survey Effort and CWD Group of Land-based Theodolite Tracking Survey
Land-based Station |
# of Survey Sessions |
Survey Effort (hh:mm) |
# CWD Groups Sighted |
CWD Group Sighting per Survey Hour |
October 2021 |
||||
Lung Kwu Chau |
1 |
06:00 |
3 |
0.5 |
Sha Chau |
1 |
06:00 |
0 |
0 |
TOTAL |
2 |
12:00 |
3 |
0.25 |
November 2021 |
||||
Lung Kwu Chau |
1 |
06:00 |
2 |
0.33 |
Sha Chau |
1 |
06:00 |
0 |
0 |
TOTAL |
2 |
12:00 |
2 |
0.17 |
December 2021 |
||||
Lung Kwu Chau |
1 |
06:00 |
3 |
0.5 |
Sha Chau |
1 |
06:00 |
0 |
0 |
TOTAL |
2 |
12:00 |
3 |
0.25 |
OVERALL |
6 |
36:00 |
8 |
0.22 |
Figure 2.9: Plots of First Sightings of All CWD Groups from Land-based Stations
Remark: Marine park excludes land area and the landward boundary generally follows the high water mark along the coastline.
PAM device has been deployed and positioned to the south of Sha Chau island inside the SCLKCMP (Figure 2.10), supplement the detection of CWD presence in the south Sha Chau area that are not recorded visually by the land-based theodolite tracking survey and to coincide the theodolite data when there is sighting from the land-based station at Sha Chau. Both C-POD and F-POD are considered as effective PAM devices in detecting CWD occurrence, and F-POD was the main PAM device deployed where feasible. In this reporting period, the F-POD has been retrieved on 11 October 2021 for data collection and was subsequently re-deployed. As the period of data collection and analysis takes more than four months, PAM results could not be reported in quarterly intervals but report for supplementing the annual CWD monitoring analysis.
During the reporting period, silt curtains were in place by the contractors for marine filling works and bored piling, in which dolphin observers were deployed by each contractor in accordance with the Marine Mammal Watching Plan (MMWP). Teams of at least two dolphin observers were deployed at 1 to 5 dolphin observation stations by the contractors for continuous monitoring of the DEZ for seawall construction (ongoing) and bored piling works (up to October 2021) in accordance with the DEZ Plan. Trainings for the proposed dolphin observers on the implementation of MMWP and DEZ monitoring were provided by the ET prior to the aforementioned works, with a cumulative total of 704 individuals being trained and the training records were kept by the ET. From the contractors’ MMWP observation records and DEZ monitoring records, no dolphin or other marine mammals were observed within or around the silt curtains or the DEZ in this reporting period. The contractors’ records were also audited by the ET during site inspection.
Audits of acoustic decoupling for construction vessels were carried out during weekly site inspection and summarised in Section 2.7. Summary of audits of SkyPier HSFs route diversion and speed control and construction vessel management are presented in Section 2.8 and Section 2.9 respectively.
In accordance with the approved EIA Report (AEIAR-185/2014) for Expansion of Hong Kong International Airport into a Three-Runway System (3RS), the gravity sewer from the airport discharge manhole to TCSPS was recommended to be upgraded by AAHK to cater for the ultimate design sewage flow from the expanded airport. It was recommended in section 6.2.1.1 of the Manual that AAHK should conduct annual monitoring for the sewage flow build-up of the gravity sewer from the airport discharge manhole to TCSPS one year before the scheduled commencement of operation of the proposed third runway. The annual monitoring results shall inform the timing of commencement of the planning of the sewer upgrading works. The sewage flow monitoring methodology paper (the Paper) was prepared, submitted and subsequently approved by EPD on 21 June 2021.
With reference to the Paper, the existing sewer to be monitored is the section between FMH7042035 (reference point A) and FMH7043286 (reference point C). A schematic diagram of the sewage system between reference point A and C is presented in Figure 2.11. The locations of these reference points are presented in Figure 2.12. To determine if the threshold of 80% of the design capacity is being reached, an approach using the Colebrook-White equation was used.
Two pipe segments between reference points A and C were identified with the lowest flow capacity and therefore selected as the benchmark for comparing the actual sewage flow of the sewers for the flow monitoring:
● Segment 1: for sewage pipelines serving the airport – the critical segment is the 1050mm sewer between manholes FMH7042032 and FMH7042033, where the 80% threshold of full flow capacity is 53,395.2 m3/day; and
● Segment 2: for the sewage pipelines serving the airport and catchment L4 – the critical segment is the 1050mm sewer between manholes FMH7043288 and FMH7043287, where the of 80% threshold of full flow capacity is 57,628.8 m3/day.
According to the Paper, segment 1 would reach its 80% full flow capacity before segment 2. Hence, segment 1 was considered the critical segment within the section between reference points A and C, and it was agreed to conduct sewage flow monitoring for segment 1 only. With the daily flow rate of SPS-1, which collects sewage arising from the Airport, is available from AAHK, desk-based flow monitoring would be conducted by comparing the daily average flow rate of SPS-1 (i.e. Q1) against the threshold of 80% of pipe capacity of segment 1 (i.e. 53,395.2 m3/day) in accordance with the following criteria:
● If Q1 ≤ 53,395.2 m3/day, planning of sewerage upgrading works can be on hold until results of next annual monitoring; and
● If Q1 > 53,395.2 m3/day, planning of sewerage upgrading works shall be considered to start and annual monitoring shall be discontinued.
Within the monitoring period, if the daily average flow rate of SPS-1 (i.e. Q1) is higher than the threshold of 53,395.2 m3/day, planning of sewerage upgrading works shall be considered to start and the annual monitoring shall be discontinued. The above approach was agreed to be adopted as part of annual monitoring for the sewage flow increment of the concerned gravity sewer in 2021 and 2022.
To fulfil the requirements as mentioned in previous section, the annual sewage flow monitoring has been started since June 2021. According to the daily flow monitoring record of SPS-1 from October to December 2021 (see Appendix C), the daily average flow of 16,319 m3/day for October 2021, 15,717 m3/day for November 2021 and 14,866 m3/day for December 2021 were well below the above-mentioned threshold of 53,395.2 m3/day. For the subsequent sets of sewage flow monitoring data for SPS-1, it will be presented in upcoming Quarterly and Annual EM&A Reports.
Site inspections of the construction works were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. Bi-weekly site inspections were also conducted by the IEC. Besides, ad-hoc site inspections were conducted by ET and IEC if environmental problems were identified, or subsequent to receipt of an environmental complaint, or as part of the investigation work. These site inspections provided a direct means to reinforce the specified environmental protection requirements and pollution control measures in construction sites.
During site inspections, environmental situation, status of implementation of pollution control and mitigation measures were observed. Environmental documents and site records, including waste disposal record, maintenance record of environmental equipment, and relevant environmental permit and licences, were also checked on-site. Observations were recorded in the site inspection checklist and passed to the contractor together with the appropriate recommended mitigation measures where necessary in order to advise contractors on environmental improvement, awareness and on-site enhancement measures. The observations were made with reference to the following information during the site inspections:
· The EIA and EM&A requirements;
· Relevant environmental protection laws, guidelines, and practice notes;
· The EP conditions and other submissions under the EP;
· Monitoring results of EM&A programme;
· Works progress and programme;
· Proposal of individual works;
· Contract specifications on environmental protection; and
· Previous site inspection results.
Good site practices were implemented in the project to enhance environmental performance. Key examples implemented in the Project are highlighted as below:
1. Sandbags and water-filled barriers were placed at site boundary to prevent muddy water discharge to nearby swale.
2. Earth bund as speed cushion was set up at haul road to reduce vehicle speed and minimise the generation of fugitive dust.
3. Environmental training was provided to workers for proper waste management and chemical waste handling procedures.
|
|
|
Use of sandbags and water-filled barriers for muddy water discharge prevention |
Use of earth bund as speed cushion for dust suppression purpose |
Provision of environmental training for site personnel |
Besides, advice was given when necessary to ensure the construction workforce were familiar with relevant procedures, and to maintain good environmental performance on site. Regular toolbox talks on environmental issues were organised for the construction workforce by the contractors to ensure understanding and proper implementation of environmental protection and pollution control mitigation measures.
A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix B.
Implementation of applicable landscape and visual mitigation measures (reference to the environmental protection measures CM1 – CM10 in Appendix B) is monitored regularly in accordance with the Manual. The implementation status of the environmental protection measures is summarised in Table 2.22. For trees which were managed under the Project during the reporting period, relevant measures have been implemented by Contracts 3302, 3503, 3508, 3602 and 3801. Contract 3802 would begin to undertake tree management measures subject to the handover of site area. Those trees which were within the Project boundary yet to be taken care by existing 3RS Contractors during the reporting period were managed by AAHK. The total number of retained trees, transplanted trees and to-be-transplanted trees under the management of Project are summarized in Table 2.23.
The total number of retained trees of the Project as of December
2021 was 52. Compared to 89 retained trees reported in the previous reporting
period, the change in number was due to the following reasons:
· Some trees near Airport North Interchange under Contract 3508 were removed due to safety concern of Airport Express Line (AEL) operation (-4 nos);
· A storage area with some trees were handed over from Contract 3801 to AAHK. The trees were excluded from the Project (-28 nos); and
· Works areas with trees were handed over from Contract 3503 to Contract 3508, of which part of the trees would be felled by Contract 3508 as planned (-5 nos).
Table 2.24 lists the affected tree ID together with the reasons for change
of retained tree status of the Project. The summary of transplanted trees is
shown in Table 2.25.
Photos of the transplanted trees are presented in Table 2.26.
Table 2.22: Landscape and Visual – Construction Phase Audit Summary
Landscape and Visual Mitigation Measures during Construction Implementation Status |
Implementation Status |
Relevant Contract(s) in the Reporting Period |
CM1- The construction area and contractor’s temporary works areas shall be minimised to avoid impacts on adjacent landscape. |
The implementation of mitigation measures were checked by ET during weekly site inspection and clarified by the Contractors during the monthly Environmental Management Meetings. Implementation of the measures CM5, CM6 and CM7 by Contractors was observed. |
3RS Project contracts |
CM2 – Reduction of construction period to practical minimum. |
||
CM3 – Phasing of the construction stage to reduce visual impacts during the construction phase. |
||
CM4 – Construction traffic (land and sea) including construction plants, construction vessels and barges shall be kept to a practical minimum. |
||
CM5 – Erection of decorative mesh screens or construction hoardings around works areas in visually unobtrusive colours. |
||
CM6 – Avoidance of excessive height and bulk of site buildings and structures |
||
CM7 – Control of night-time lighting by hooding all lights and through minimisation of night working periods |
||
CM8 – All existing trees shall be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas |
Tree Protection Specifications have been provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project.
The Contractors’ performance on the implementation of the trees maintenance and protection measures were observed and checked by the ET weekly during construction period. |
3302, 3503, 3508, 3602, 3801
3802 (To be implemented) |
CM9 – Trees unavoidably affected by the works shall be transplanted where practical. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, if applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme |
Tree Transplanting Specifications have been provided in the relevant Contract Specifications respectively for implementation by the Contractors under the Project where trees will unavoidably be affected by the construction works.
The Contractors were required to submit Method Statements for tree transplanting prior to the transplanting works. Tree inspections were conducted by ET to check the tree transplanting works implemented by the Contractors on site.
The Contractors’ performance on the implementation of trees maintenance and protection measures on transplanted trees were observed and checked by the ET bi-monthly during the 12-month establishment period after the completion of each batch of transplanting works.
Long term management of the transplanted trees were currently monitored by ET annually. |
3503, 3508 3801
3802 (To be implemented) |
CM 10 – Land formation works shall be followed with advanced hydroseeding around taxiways and runways as soon as practical |
To be implemented around taxiways and runways as soon as practicable. |
To be implemented |
Table 2.23: Summary of the Number of Retained, Transplanted and To-be-transplanted Trees in the Reporting Period
Existing |
|
|
|
|
Contract |
Retain (nos.) |
Transplanted (nos.) |
To-be-transplanted (nos.) |
|
Establishment Period |
Maintenance Period |
|||
3302 |
9 |
0 |
0 |
0 |
3503 |
0 |
6 |
3 |
0 |
3508(1) |
24 |
12 |
0 |
0 |
3602 |
2 |
0 |
0 |
0 |
3801 |
17 |
0 |
5 (2) |
0 |
Sub-total |
52 |
18 |
8 |
0 |
Provisional |
|
|
|
|
Contract |
Retain (nos.) |
Transplanted (nos.) |
To-be-transplanted (nos.) |
|
3508(1) |
51 |
0 |
10 |
|
Sub-total |
51 |
0 |
10 |
|
Grand Total |
103 |
26 |
10 |
Note:
(1) As some of the site areas have been handed over to Contract 3508, existing trees to be managed by Contract 3508 is subject to change after initial tree surveys for each batch of handed over site areas have been conducted by the Contractor.
(2) Three transplanted trees (CT1194, CT1794 and CT1795) were subsequently fell after transplantation. Please refer to Table 2.25 for details.
Table 2.24: Summary of the Tree Status Updated in the Reporting Period
Tree ID(s) |
Contract
|
Previous Status (Sep 2021) |
Current Status (Dec 2021) |
Remarks |
Impact to Retain Tree Number |
T1462, T1463, T1464, T1467 |
3508 |
Retain |
Fell |
4 nos. of trees were removed due to safety concern of Airport Express Line (AEL) operation. |
- 4 nos. |
CT1843, CT1844, CT1845, CT1846, CT1847, CT1848, CT1849, CT1850, CT1851, CT1852, CT1853, CT1859, CT1860, CT1861, CT1862, CT1865, CT1866, CT1867, CT1868, CT1869, CT1870, CT1871, CT1872, CT1873, CT1874, CT1876, CT1877, CT1878 |
3801 |
Retain |
Excluded from the Project |
28 nos. of trees were handed over to AAHK. The trees were excluded from the Project. |
- 28 nos. |
T3030, T3031, T3189, T3191, T3194 |
3508 |
Retain |
To-be felled |
5 nos. of trees were handed over from Contract 3503 to Contract 3508 and would be felled by Contract 3508 as planned. |
- 5 nos. |
Table 2.25: Summary of the Transplanted Trees Updated in the Reporting Period
Tree ID |
Transplant Date |
Management Stage |
Management Agency |
Remarks |
CT276 |
3 May 2018 |
Establishment period 4 May 2018 – May 2019 |
Contract 3801 |
Next inspection will be conducted in February 2022. Photos of the last inspection in February 2021 can be referred to Table 7.7 of Monthly EM&A Report No. 62. |
Long Term Management period Jun 2019 – May 2028 |
Southern Landside Petrol Filling Station |
|||
CT1253 |
4 May 2018 |
Establishment period 5 May 2018 – May 2019 |
Contract 3801 |
|
Long Term Management period Jun 2019 – May 2028 |
Southern Landside Petrol Filling Station |
|||
T835 |
22 Jan 2020 |
Establishment period 23 Jan 2020 – Jan 2021 |
Contract 3503
|
Next inspection will be conducted in February 2022. Photos of the last inspection in February 2021 can be referred to Table 7.7 of Monthly EM&A Report No. 62. |
Long Term Management period Feb 2021 – Jan 2030 |
||||
T836 |
13 Dec 2019 |
Establishment period 14 Dec 2020 – Jan 2021 |
||
Long Term Management period Feb 2021 – Jan 2030 |
||||
T838 |
22 Jan 2020 |
Establishment period 23 Jan 2020 – Jan 2021 |
||
Long Term Management period Feb 2021 – Jan 2030 |
||||
T812 |
21 Dec 2020 |
Establishment period 22 Dec 2020 – Dec 2021 |
Contract 3503
|
Next inspection will be conducted in February 2022. Photos of the last inspection in December 2021 were shown in Table 2.26. |
T814 |
20 Dec 2020 |
Establishment period 21 Dec 2020 – Dec 2021 |
||
T815 |
15 Dec 2020 |
Establishment period 16 Dec 2020 – Dec 2021 |
||
T829 |
18 Dec 2020 |
Establishment period 19 Dec 2020 – Dec 2021 |
||
T830 |
14 Dec 2020 |
Establishment period 15 Dec 2020 – Dec 2021 |
||
T831 |
19 Dec 2020 |
Establishment period 20 Dec 2020 – Dec 2021 |
||
T1493 |
6 Jul 2021 |
Establishment period 7 Jul 2021 – Jul 2022 |
Contract 3508
|
Next inspection will be conducted in January 2022. Photos of the last inspection in November 2021 can be referred to Table 7.7 of the Construction Phase Monthly EM&A Report No. 71. |
T1494 |
6 Jul 2021 |
Establishment period 7 Jul 2021 – Jul 2022
|
||
T1495 |
10 Jul 2021 |
Establishment period 11 Jul 2021 – Jul 2022
|
||
T1496 |
5 Jul 2021 |
Establishment period 6 Jul 2021 – Jul 2022 |
||
T1497 |
5 Jul 2021 |
Establishment period 6 Jul 2021 – Jul 2022 |
||
T1498 |
29 Jun 2021 |
Establishment period 30 Jun 2021 – Jul 2022 |
||
T1499 |
29 Jun 2021 |
Establishment period 30 Jun 2021 – Jul 2022 |
||
T1500 |
30 Jun 2021 |
Establishment period 1 Jul 2021 – Jul 2022 |
||
T1501 |
30 Jun 2021 |
Establishment period 1 Jul 2021 – Jul 2022 |
||
T1502 |
5 Jul 2021 |
Establishment period 6 Jul 2021 – Jul 2022 |
||
T1503 |
6 Jul 2021 |
Establishment period 7 Jul 2021 – Jul 2022 |
||
T1504 |
24 Jun 2021 |
Establishment period 25 Jun 2021 – Jul 2022 |
||
CT1194 |
4 May 2018 |
Establishment period 5 May 2018 – May 2019 |
Contract 3801 |
NA |
Long Term Management period Jun 2019 – May 2028 |
Southern Landside Petrol Filling Station |
Uprooted and collapsed due to Typhoon Higos on 18 August 2020. Tree removal was conducted as recommended by tree specialist of the contractor of Southern Landside Petrol Filing Station.
|
||
CT1794 |
3 May 2018 |
Establishment period 4 May 2018 – May 2019 |
Contract 3801 |
NA |
Long Term Management period Jun 2019 – May 2028 |
AsiaWorld-Expo |
The tree within the land parcel was acquired by the government for construction of emergency hospital to handle COVID19 pandemic at AsiaWorld-Expo. The tree was felled in late 2020. |
||
CT1795 |
3 May 2018 |
Establishment period 4 May 2018 – May 2019 |
Contract 3801 |
NA |
Long Term Management period Jun 2019 – May 2028 |
AsiaWorld-Expo |
The tree within the land parcel was acquired by the government for construction of emergency hospital to handle COVID19 pandemic at AsiaWorld-Expo. The tree was felled in late 2020. |
Table 2.26: Photos of the Existing Transplanted Trees in the Reporting Period
Under 12-month Establishment Period: |
||
|
|
|
T812 |
T814 |
T815 |
|
|
|
T829 |
T830 |
T831 |
The Supplementary CAP was submitted to EPD pursuant to EP Condition 2.20. The CARs for Golf Course and T2 Emergency Power Supply Systems (EPSS) were submitted to EPD in accordance with EP Condition 1.9 and the Supplementary CAP in which no land contamination issues were identified. EPD has issued no further comment for aforesaid CARs. No leakage was found after the removal of underground fuel pipelines and all required additional photos have been submitted to EPD.
According to the approved supplementary CAP, there are 3 remaining locations where site re-appraisal / additional site investigation are proposed. Based on the latest construction information, which has been presented in Appendix A Implementation Schedule of the approved CARs for T2 EPSS, there is no development programme for these locations at this stage. As such, the status of site re-appraisal/ additional site investigation will be further updated upon latest development programme is available.
The Marine Travel Routes and Management Plan for High Speed Ferries of SkyPier (the SkyPier Plan) was submitted to the Advisory Council on the Environment for comment and subsequently submitted to and approved by EPD in November 2015 under EP Condition 2.10. The approved SkyPier Plan is available on the dedicated website of the Project. In the SkyPier Plan, AAHK has committed to implement the mitigation measure of requiring HSFs of SkyPier travelling between HKIA and Zhuhai / Macau to start diverting the route with associated speed control across the area, i.e. Speed Control Zone (SCZ), with high CWD abundance. The route diversion and speed restriction at the SCZ have been implemented since 28 December 2015.
Due to the COVID-19 pandemic, all SkyPier HSF services to/from Zhuhai and Macau have been suspended from 25 March 2020 until further notice. Limited HSF services from other destination, which does not require the use of the diverted route, were provided starting from 28 October 2020.
No ferry movement between HKIA SkyPier to/from Zhuhai and Macau was recorded in the reporting period. The daily movements of all SkyPier HSFs in the reporting period, including those not using the diverted route, ranged between 1 and 7, which fell within the maximum daily cap number of 125.
The construction works of the Hong Kong Offshore LNG Terminal Project were carried out from Q3 to Q4 2021. However, there was no implication to the route diversion operation of the SkyPier HSFs since all SkyPier HSF services to /from Zhuhai and Macau were suspended. ET will continue to closely monitor the implementation of the SkyPier Plan.
On the implementation of the updated Marine Travel Routes and Management Plan for Construction and Associated Vessels (MTRMP-CAV), the Maritime Surveillance System (MSS) automatically recorded deviation cases such as speeding, entering no entry zone, and not traveling through the designated gates. ET conducted bi-weekly audit of relevant information including AIS data, vessel tracks and other relevant records to ensure sufficient information were provided by the system and the contractors complied with the requirements of the MTRMP-CAV. The contactors submitted 3-month rolling vessel plans for construction vessel activities to AAHK in order to help maintain the number of construction vessels to a practicable minimum. The IEC also performed audit on the compliance of the requirements as part of the EM&A programme.
During the reporting period, deviations including speeding within the works area, entry from non-designated gates, and entering no-entry zones were identified. After investigation by the contractor’s Construction Traffic Control Centre (CTCC) representatives, all the concerned captains were reminded to comply with the requirements of the MTRMP-CAV.
A total of 6 skipper training workshops were held by ET during the reporting period and 17 concerned captains of construction vessels associated with the 3RS contracts were trained to familiarise them with the predefined routes, general education on local cetaceans, guidelines for avoiding adverse water quality impact, the required environmental practices / measures while operating construction and associated vessels under the Project, and guidelines for operating vessels safely in the presence of CWDs. Another 7 skipper training workshops were held with 8 captains by contractors’ Environmental Officers and competency tests were conducted subsequently with the trained captains by ET.
With reference to Appendix E of the Manual, it is noted that the key assumptions adopted in approved EIA report for the construction phase are still valid and no major changes are involved. The environmental mitigation measures recommended in the approved EIA Report remain applicable and shall be implemented in undertaking construction works for the Project.
During the reporting period, environmental related licenses and permits required for the construction activities were checked. No non-compliance with environmental statutory requirements was recorded.
Seven environmental complaints were received during the reporting period. All were attended to and investigations were conducted by the ET in accordance with the Manual and the Complaint Management Plan. A summary of the complaints and analyses is presented in Table 3.1.
Table 3.1: Summary of Environmental Complaints
Date of Complaint Received |
Details |
Analysis/ Remedial Actions |
Status |
6 October 2021 |
A complaint regarding dust issue at 3RS construction site area was received. |
A complaint regarding dust issue at 3RS construction site area was received on 6 October 2021.The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. The ET identified the related contractors and requested them to provide information regarding the complaint.
According to the information provided by the contractors, all reported that they had provided water spraying on site and their watering records within October 2021 showed they had conducted water spraying at all active works area in accordance with the implementation schedule in the Updated EM&A Manual. Based on the ET’s weekly site inspections, no item related to insufficient water spraying was recorded on the checklists for all works contracts. A joint ad-hoc inspection by EPD, ET, IEC and AAHK was also carried out at 3RS reclaimed land after receiving the complaint, in which no adverse comments related to insufficient water spraying was identified. Nevertheless, all air quality monitoring results from 4 to 8 October 2021 were within the corresponding Action and Limit Levels. ET reminded all contractors to continue implementing dust suppression measures, especially sufficient water spraying at the site area in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the complaint case was considered closed. |
Closed |
29 October 2021 |
A complaint regarding dust issue at 3RS construction site area near northeastern quay bus station was received. |
A complaint regarding dust issue at 3RS construction site area near northeastern quay bus station was received on 29 October 2021. The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. From the two videos provided by the complainant, ET recognized the location, identified a related contractor and requested them to provide information regarding the complaint.
According to the information received, the concerned location is the haul road that link to the bus station at 3RS northeastern quay. Based on the ET’s weekly site inspections, no item related to dust issue on the above-mentioned haul road was recorded on the site environmental checklist. And during a joint ad-hoc inspection as conducted by EPD, ET, IEC, and AAHK around the public haul road near bus station of northeastern quay, water spraying at the concerned haul road was observed. Nevertheless, all air quality monitoring results from 27 October to 2 November 2021 were within the corresponding Action and Limit Levels. ET would continue to monitor the contractor’s dust control layout plan and reminded all contractors to properly implement dust suppression measures, especially water spraying at their site area in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
7 November 2021 |
A complaint regarding dust issue at 3RS construction site area was received. |
A complaint regarding dust issue at 3RS construction site area was received on 7 November 2021. The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. From the photos provided by the complainant, ET recognized the location, identified a related contractor and requested them to provide information regarding the complaint. According to the contractor, water tankers were arranged to carry out water spraying for the site. The contractor also reviewed their dust control management plan and provided enhancement measures including the designation of a water tanker focusing on the watering along the concerned haul road, and extra water spraying at the related area by workers.
At ET’s weekly site inspection in early November 2021, dust was observed during vehicle movement on haul road and the contractor rectified the issue by providing photos on the next day documenting water spraying on haul road. A joint ad-hoc inspection by EPD, ET, IEC, and AAHK was also conducted around the concerned location after receiving the complaint, in which water spraying for the concerned haul road was observed. In parallel, all air quality monitoring results from 1 November to 8 November 2021 were within the corresponding Action and Limit Levels. ET would continue to monitor contractor’s performance of water spraying in accordance with their dust control management plan and reminded all contractors to properly implement dust mitigation measures, especially water spraying on the haul road in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
15 November 2021 |
Two emails regarding dust issue were received. |
Two emails regarding dust issue were received on 15 November 2021. The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. From the photos and videos provided by the complainant, ET recognized the location, identified a related contractor and requested them to provide information. According to the contractor, three water tankers were arranged to carry out water spraying for their site and one of the water tankers was designated to focus on watering along the concerned haul road. Extra water spraying on the concerned haul road by workers was also arranged.
At one of the ET’s weekly site inspection, dust was observed during vehicle movement on haul road and was rectified by the contractor subsequently; and at another regular inspection, no item related to dust issue was recorded. During an ad-hoc inspection by EPD, ET, IEC and AAHK, water spraying at the concerned haul road was observed. The ET also checked air quality monitoring results from before and after the receiving of the complaint and noted all results were within the corresponding Action and Limit Levels. ET would continue to monitor contractor’s performance of water spraying in accordance with their management plan and reminded all contractors to properly implement dust mitigation measures, especially water spraying on the haul road in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
24 November 2021 |
A complaint regarding Non-road Mobile Machinery (NRMM) issue at 3RS contractor’s works area was received. |
A complaint regarding Non-road Mobile Machinery (NRMM) issue at 3RS contractor’s works area was received on 24 November 2021. The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. From the photos provided by the complainant, ET recognized the location, identified a contractor and requested them to provide information regarding the complaint. According to the contractor, their concerned concrete pump truck (special purpose vehicle) has obtained a valid NRMM label. The contractor provided relevant photos of their concrete pump truck and NRMM label. The ET and IEC conducted NRMM random checks on the contractor during weekly site inspections and the ET reminded the contractor to display NRMM labels at conspicuous positions on their machines or vehicles and to strictly follow the NRMM labelling requirements and to have the label sizes of at least 200mm in width and 130 mm in height. The ET reminded all contractors to check and ensure proper NRMM labels are displayed on their on-site vehicles and machines. Hence the complaint case was considered closed. |
|
1 December 2021 |
A complaint regarding suspected dump truck for garbage disposal that was not properly covered was received. |
A complaint regarding suspected dump truck for garbage disposal that was not properly covered and leaving the 3RS construction site area via pier was received on 1 December 2021. The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. The ET recognized the location, identified the related contractors and requested them to provide information. According to the replies, one reported they did not have dump trucks for garbage disposal leaving the alleged pier during the period of investigation. Another contractor replied they had dump trucks for the disposal of garbage going to landfill by marine route during the period of investigation, stating their dump trucks were covered entirely and checked by site supervisors before leaving their construction site and that refresher trainings on the proper covering of dump trucks were also provided to their site foremen and frontline workers. Based on the ET’s weekly site inspections, no item related to the covering of dump trucks was recorded. And during an ad-hoc inspection by EPD, ET, IEC and AAHK, it was observed that all dump trucks were properly covered when embarking Roro barges. ET would continue to monitor contractor’s performance and reminded all contractors to ensure the proper covering of dump trucks for garbage disposal. Hence, the case was considered closed. |
|
13 December 2021 |
A complaint regarding muddy water was received. |
A complaint regarding muddy water was received on 13 December 2021. The case was investigated by ET in accordance with the Manual and the Complaint Management Plan of the Project. From the photo provided by the complainant, ET recognized the location, identified a related contractor and requested them to provide information. According to the reply, there were work activities at the alleged location during the period of investigation and that silt curtain was provided to contain muddy water. The contractor also indicated provision of mitigation measures including daily visual check at their works area and training on water control measures to frontline staff. At ET’s site inspections and ad-hoc inspection by EPD, ET, IEC and AAHK, there was no observation on muddy water. For the installation of silt curtain, ET reminded the contractor to maintain it properly. The ET also checked water quality monitoring results from before and after the receiving of the complaint and noted all results were within the corresponding Action and Limit Levels. ET would continue to monitor contractor’s performance and reminded all contractors to properly implement water quality mitigation measures in accordance with the implementation schedule in the Updated EM&A Manual. Hence, the case was considered closed. |
|
A contractor reported in October 2021 that they had pleaded guilty in court and was fined by the court regarding summonses as laid by EPD upon a dust control emission incident for reclamation works in April 2021 contravening the Air Pollution Control Ordinance Cap. 311.
Cumulative statistics on valid exceedance, non-compliance, complaints, notifications of summons and status of prosecutions are summarised in Table 3.2 and Table 3.3.
Table 3.2: Statistics for Valid Exceedances for the Environmental Monitoring
|
|
Total No. Recorded in the Reporting Period |
Total No. Recorded since the Project Commenced |
1-hr TSP |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Noise |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Waste |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Water |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
CWD |
Action Level |
0 |
0 |
|
Limit Level |
0 |
0 |
Remark: Non-project related triggers of Action or Limit Level are not shown in this table.
Table 3.3: Statistics for Non-compliance, Complaints, Notifications of Summons and Prosecution
Reporting Period |
Cumulative Statistics |
||||
|
Non-compliance |
Complaints |
Notifications of Summons |
Prosecutions |
|
This reporting period |
0 |
7 |
1 |
1 |
|
From 28 December 2015 to end of the reporting period |
0 |
47 |
2 |
2 |
|
In this quarterly period from 1 October 2021 to 31 December 2021, the EM&A programme has been implemented as planned, including 96 sets of air quality measurements, 52 sets of construction noise measurements, 37 sets of water quality measurements, 6 complete sets of vessel line transect surveys and 6 days of land-based theodolite tracking survey effort for CWD monitoring, as well as environmental site inspections and waste monitoring for the Project’s construction works.
The key activities of the Project carried out in the reporting period included reclamation works and land-based works. Works in the reclamation areas included marine filling, seawall and facilities construction, together with runway and associated works such as bored piling for approach lights. Land-based works on existing airport island involved mainly airfield works, foundation and substructure work for Terminal 2 expansion, modification and tunnel work for APM and BHS, and preparation work for utilities, with activities include site establishment, site office construction, road and drainage works, cable ducting, demolition, piling, and excavation works.
Monitoring results of construction dust, construction noise, construction waste, and CWD monitoring did not trigger the corresponding Action and Limit Levels during the reporting period.
All site observations made by the ET were recorded in the site inspection checklists and passed to the contractor together with the recommended follow-up actions.
For water quality, the water quality monitoring results for all parameters, except SS, obtained during the reporting period were within the corresponding Action and Limit Levels stipulated in the EM&A programme. Relevant investigation and follow-up actions will be conducted according to the EM&A programme if the corresponding Action and Limit Levels are triggered. For SS, some testing results triggered the relevant Action Levels, and the corresponding investigations were conducted accordingly. The investigation findings concluded that the cases were not related to the Project. In summary, the construction activities undertaken during the reporting period did not introduce adverse impact to all water quality sensitive receivers.
No HSF movement between HKIA SkyPier to/from Zhuhai and Macau was recorded during the reporting period. Therefore, no deviation was recorded in the HSF monitoring during the reporting period.
During the reporting period, ET conducted bi-weekly audit of the MSS to ensure the system recorded all deviation cases accurately and the contractors fully complied with the requirements of the MTRMP-CAV. Six skipper training workshops were held by ET and 7 skipper training workshops were held by contractors’ Environmental Officers during the reporting period and competency tests were conducted subsequently with the trained skippers by ET.
On the implementation of MMWP and DEZ Plan, dolphin observers were deployed by the contractors in accordance with the plans. No dolphin or other marine mammals were observed within or around the silt curtains or the DEZ in this reporting period. Audits of contractors’ implementation and records, and also acoustic decoupling for construction vessels were carried out by the ET during site inspection.
The recommended environmental mitigation measures, as included in the EM&A programme, were effectively implemented during the reporting period. Also, the EM&A programme implemented by the ET has effectively monitored the construction activities and ensured the proper implementation of mitigation measures.
[1] The Manual is available on the Project’s dedicated website (accessible at: http://env.threerunwaysystem.com/en/index.html)